The Preserve Project Nails It

Site Just Before Clearing & Grading Began

Clearing of undercut and other materials

Clearing of the project jobsite began by first clearing and grading the lot so that the subgrade for the building pad could be prepared.

Subgrade work started

Backfill for the parking lot area

Grading and backfill work began at the job site for the parking lot area and excavation for the building pad as well.

Excavation of Basement Started

Rock removal crews working on Excavation

The first work of the project involved the removal of rock and excavation for the future basement. The excavation lowered the original grade of the building site down 14 feet.

Soil Nail Example

Tecco Mesh System over Geotectile Fabric

Finished product of the geo fabric and soil nails

In what will be the future basement area, the crews installed a geo fabric with Soil Nails. These “nails” are spiral pins that are driven into a bank of earth at various depths to essentially lock the geo fabric and geogrid-style material shown above into the retaining wall. As the Soil Nails are driven into the components and the wall, the pressure locks everything into place.

Town Center of the Preserve in background

The Preserve Office Building will meet the design elements of the local area once completed

This entry was posted in Birmingham, AL, Building Pad, Civil Engineering, Construction, Erosion Control, Grading, Stewart Perry, The Preserve and tagged , , , , , , , , , , , . Bookmark the permalink.

One Response to The Preserve Project Nails It

  1. Pingback: Top Down Wall Construction (Soil Nails) « Planting Acorns

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>